BIM
Revit / BIM Task Request Log & Tracker
BIM-00048

Request details

Closed

Read-only view. To add an update or work with attachments, the requester must use the private tracking link supplied when the request was submitted.

Go To Dashboard

Request details

RequesterAshley Reilly
ProjectK322
DisciplineArchitecture
Task TypeFamily Creation / Modification
PriorityNormal
Due Date2020-10-07
Submitted2020-09-25 00:00:00
Last Updated2020-09-25 00:00:00
Re: Adaptive Entrance - @ East side of entrance family, all points are at 4" (No Angle/ Slope). Also, if possible to add the joints at the panel locations. Also, family is slightly skewed - please make sure it is straight in elevation view.

Public updates

No public updates yet.